Commissioning and operation status of the MAX IV 3 GeV storage ring vacuum system

Marek Grabski, Eshraq Al-Dmour

Research output: Contribution to journalArticlepeer-review

Abstract

The 3 GeV electron storage ring of the MAX IV laboratory is the first storage-ring-based synchrotron radiation facility with the inner surface of almost all the vacuum chambers along its circumference coated with non-evaporable getter (NEG) thin film. The coating provides a low dynamic outgassing rate and pumping of active gases. As the NEG coating was applied on an unprecedented scale, there were doubts concerning the storage ring performance. Fast conditioning of the vacuum system and over five years of reliable accelerator operation have demonstrated that the chosen design proved to be good and does not impose limits on the operation. The vacuum system performance is comparable with or better than that of other similar facilities around the world, where conventional designs were implemented. Observed pressure levels are low, and the electron beam lifetime is long and not limited by residual gas density. A summary of the vacuum performance is presented.

Original languageEnglish
Pages (from-to)718-731
Number of pages14
JournalJournal of Synchrotron Radiation
Volume28
DOIs
Publication statusPublished - 2021 May 1

Subject classification (UKÄ)

  • Subatomic Physics

Free keywords

  • MAX IV
  • NEG coatings
  • synchrotron light source
  • thin films
  • vacuum

Fingerprint

Dive into the research topics of 'Commissioning and operation status of the MAX IV 3 GeV storage ring vacuum system'. Together they form a unique fingerprint.