Verification of Governor Response During Normal Operation

Forskningsoutput: KonferensbidragKonferenspaper, ej i proceeding/ej förlagsutgivet

Abstract

This paper describes one approach to
verification of governor response during normal operation.
It is based on field tests carried out in four
hydro power plants in the Sweden. The experiments
were carried out in September 1976 but have not
been published internationally until now. Additional
analysis and simulations were carried out during the
preparation of this paper in July 2002.